某财税大楼工程支模架搭设施工方案.doc
某财税大楼工程支模架搭设施工方案编制 审核 批准 某建设实业有限公司某财税大楼顶目部 二00三年五月八日1、工程概况 某财税大楼工程为17层框架剪力墙结构,总建筑面积17500m2;裙房3868m2。各现浇楼面层高一般为3.55.85m,板厚100160。中庭和通廊高度达到9.4512.95m。 2、脚手架设计2.1南面中庭顶板支模架设计南面中庭顶板支模架搭设高度12.85m,楼板厚度100mm,最大梁高800mm。施工中支模架采用483.5焊缝钢管搭设,模板采用18厚胶合板,设计步距1700mm(8步架),跨距板下为800800,梁下为500500,现对立杆稳定性验算如下2.1.1荷载计算2.1.1.1单根脚手架自重立杆 12.8537.6483N(板) 12.1537.6456N(梁)横杆 0.88237.6481N(板) 0.58237.6300N(板)扣件 8213.2518.4214.6332N4834813321.296KN(板)4563003321088N(梁)2.1.1.2模板自重标准 1KN0.80.80.64KN(板)1KN0.50.50.25KN(梁)2.1.1.3新浇砼楼面自重 2.49.80.10.80.81.51KN(板)2.49.8(0.80.50.40.10.50.1)3.88KN(梁)2.1.1.4钢筋自重 1.10.80.80.7kN(板) (82.990.541.210.532.40.395)9.8150N(梁)NGK1.29611.510.74.506KN(板)NGK1.0880.253.880.155.368KN(梁)2.1.1.5施工及设备荷载标准NQK 30.80.81.92KN(板)NQK 30.50.50.75KN(梁)单根立杆轴力为N11.24.5061.41.928.1KN(板)N21.25.3681.40.757.49KN(梁)因N1N2,只需验算N1即可。2.1.2立杆稳定性验算L0h2a1.720.152m i1.58cm入 L0/i2100/1.58126.6 8.1103查表得 j 0.374 NjA 0.374489 75N/mm2 fc 205N/mm2钢管稳定性均满足稳定要求。2.2北面中庭和连廊支模架设计北面中庭和连廊搭设高度9.3m,板厚150mm,梁截面小于400800,施工中支模架采用483.5焊缝钢管搭设,模板采用18厚胶合板,设计跨距12001200,步距1700mm(6步架),梁下为600600,现对立杆稳定性验算如下2.2.1荷载计算2.2.1.1单根脚手架自重立杆 9.337.6350N(板) 8.6537.6325N(梁)横杆 1.28237.6720N(板) 0.68237.6360N(梁)扣件 6213.2318.4114.6228N3507202281.298KN(板)3253602280.913KN(梁)2.2.1.2模板自重标准 1KN1.21.21.44KN(板)1KN0.60.60.36KN(梁)2.2.1.3新浇砼楼面自重 2.49.80.11.21.23.386KN(板)2.49.8(0.80.60.40.10.60.2)4.8KN(梁)2.2.1.4钢筋自重 1.11.21.21.58KN(板) (82.990.641.210.632.40.395)9.8197N(梁)NGK1.2981.443.3861.587.704KN(板)NGK0.9130.364.80.1976.27KN(梁)2.2.1.5 施工及设备荷载标准NQK 31.21.24.32KN(板)NQK 30.60.61.08KN(梁)单根立杆轴力为N11.27.7041.44.3215.3KN(板)N21.26.271.41.089.036KN(梁)因N1N2,只需验算N1即可。2.2.2立杆稳定性验算L0h2a1.720.152m i1.58cm入 L0/i2100/1.58126.6 15.3103查表得 j 0.384 NjA 0.384489 81.5N/mm2 fc 205N/mm2钢管稳定性均满足稳定要求。2.3 一层、二层、八层、十五、十六层支模架设计搭设高度5m以下,板厚小于160mm,梁截面小于400800。 施工中支模架采用483.5焊缝钢管搭设,模板采用18厚胶合板,设计跨距15001500,步距1700mm(3步架),梁下为750750,现对立杆稳定性验算如下2.3.1荷载计算2.3.1.1单根脚手架自重立杆 4.8437.6182N(板) 4.237.6158N(梁)横杆 1.53237.6338N(板) 0.753237.6164N(梁)扣件 3213.218.498N182338980.618KN(板)158164980.42KN(梁)2.3.1.2模板自重标准 1KN1.51.52.25KN(板)1KN0.750.750.56KN(梁)2.3.1.3新浇砼楼面自重 2.49.80.11.51.55.29KN(板)2.49.8(0.80.750.40.10.750.35)6.26KN(梁)2.3.1.4钢筋自重 1.11.51.52.475KN(板) (82.990.7541.210.7572.40.395)9.8276N(梁)NGK0.6182.255.292.47510.633KN(板)NGK0.420.566.260.2767.516KN(梁)2.3.1.5 施工及设备荷载标准NQK 31.51.56.75KN(板)NQK 30.750.751.69KN(梁)单根立杆轴力为N11.210.6331.46.7522.2KN(板)N21.27.5161.41.6911.38KN(梁)因N1N2,只需验算N1即可。2.3.2立杆稳定性验算L0h2a1.720.152m i1.58cm入 L0/i2100/1.58126.6 22.2103查表得 j 0.399 NjA 0.399489 113.8N/mm2 fc 205N/mm2钢管稳定性均满足稳定要求。2.4 标准层支模架设计标准层搭设高度3.5m以下,板厚100mm,梁截面小于400800。 施工中支模架采用483.5焊缝钢管搭设,模板采用18厚胶合板,设计跨距17001700,步距1750mm(2步架),梁下为850850,现对立杆稳定性验算如下2.4.1荷载计算2.4.1.1单根脚手架自重立杆 3.437.6127N(板) 2.737.6102N(梁)横杆 1.73237.6383N(板) 0.853237.6192N(梁)扣件 3213.218.498N127383980.608KN(板)102192980.392KN(梁)2.4.1.2模板自重标准 1KN1.71.72.89KN(板)1KN0.850.850.73KN(梁)2.4.1.3新浇砼楼面自重 2.49.80.11.71.76.8KN(板)2.49.8(0.80.850.40.10.850.45)7.3KN(梁)2.4.1.4钢筋自重 1.11.71.73.179KN(板)(82.990.7541.210.7572.40.395)9.811000.450.85697N(梁)NGK0.6082.896.83.17913.477KN(板)NGK0.3920.737.30.6979.119KN(梁)2.4.1.5 施工及设备荷载标准NQK 31.71.78.67KN(板)NQK 30.850.852.17KN(梁)单根立杆轴力为N11.213.4771.48.6728.31KN(板)N21.29.1191.42.1713.98KN(梁)因N1N2,只需验算N1即可。2.4.2立杆稳定性验算L0h2a1.720.152m i1.58cm入 L0/i2100/1.58126.6 28.31103查表得 j 0.404 NjA 0.404489 143.3N/mm2 fc 205N/mm2钢管稳定性均满足稳定要求。2.5 十七层支模架设计十七层层高5.85m,板厚150mm,梁截面小于400800。 施工中支模架采用483.5焊缝钢管搭设,模板采用18厚胶合板,设计跨距15001500,步距1750mm(4步架),梁下为750750,现对立杆稳定性验算如下2.5.1荷载计算2.5.1.1单根脚手架自重立杆 5.737.6214N(板) 537.6188N(梁)横杆 1.55237.6564N(板) 0.754237.6225N(梁)扣件 5213.218.42169N2145641690.947KN(板)1882251690.582KN(梁)2.5.1.2模板自重标准 1KN1.51.52.25KN(板)1KN0.750.750.56KN(梁)2.5.1.3新浇砼楼面自重 2.49.80.11.51.55.29KN(板)2.49.8(0.80.750.40.10.750.35)6.26KN(梁)2.5.1.4钢筋自重 1.11.51.52.47KN(板)(82.990.7541.210.7572.40.395)9.811000.350.75565N(梁)NGK0.9472.255.292.4710.96KN(板)NGK0.5820.566.260.5657.967KN(梁)2.5.1.5 施工及设备荷载标准NQK 31.51.56.75KN(板)NQK 30.750.751.69KN(梁)单根立杆轴力为N11.210.961.46.7522.602KN(板)N21.29.671.41.6913.97KN(梁)因N1N2,只需验算N1即可。2.5.2立杆稳定性验算L0h2a1.720.152m i1.58cm入 L0/i2100/1.58126.6 28.31103查表得 j 0.393 NjA 0.393489 147N/mm2 fc 205N/mm2钢管稳定性均满足稳定要求。 3、脚手搭设、使用、拆除的一般要求。3.1支模架搭设、使用、拆除的一般规定 3.1.1搭设规定 在搭设之前,必须对进场的脚手架配件进行严格的检查,禁止使用规格和质量不合格的杆配件。 3.1.2每搭设完一步脚手架,应校正步距、纵距、横距及立杆的垂直度。 3.1.3每道剪力撑、横向斜撑搭设宽度不应小于4跨,且不应小于6米,斜杆与地面的倾角宜在4560度之间,并应随立杆、纵向和横向水平杆同时搭设,各底层斜面杆下端均必须支承在垫块或垫板上。 3.1.4立杆上的对接扣件应交错布置两根相邻立杆的接头不应设置在同步内,同步内隔一根立杆的两个相隔接头在高度方向错开的距离不宜小于500mm;每接头中心至主节点的距离不宜大于步距的1/3。 3.1.5工人在架上进行搭设作业时,作业面上宜铺设必要数量的脚手板并临时固定。工人必须戴安全帽和佩挂安全带,不得单人进行装设较重杆配件和其它易发生失衡、脱手、碰撞、滑跌等不安全作业。 3.1.6在搭设中不得随意改变构架设计,减少杆配件设置和对立杆纵距作100mm的构架尺寸放大。确有实际情况,需要对构架作调整时,应提交技术主管人员解决。3.2使用规定 3.2.1作业人员在架上的最大作业高度应以可进行正常操作为度,禁止在架板上加垫器物或单块脚手板以增加操作高度。在作业中,禁止随意拆除脚手架的基本构架杆件、整体性杆件、连接紧固件和连墙件。确因操作要求临时拆除时,必须经主管人员同意,采取相应弥补措施,并在作业完毕后,及时予以恢复。 3.2.2工人在架上作业中,应注意自我安全保护和他人的安全,避免发生碰撞、闪失和落物,严禁在架上戏闹和坐在栏杆上等不安全处休息。 3.2.3每班工人上架作业时,应先行检查有无影响安全作业的问题存在,在排除和解决后方许开始作业。在作业中发现有不安全的情况和迹向时,应立即停止作业,进行检查,解决以后才能恢复正常作业,发现有异常和危险情况时,应立即通知所有架上人员撤离。 3.2.4在每架的作业完成之后,必须将架上剩余材料物品移至地面,在任何情况下,严禁自架上向下抛掷材料物品和倾倒垃圾。3.3、拆除规定 3.3.1拆除作业必须由上而下逐层进行,严禁上下同时作业。 3.3.2在拆除过程式中,凡已松开连接的杆配件应及时拆除运走,避免误扶和误靠已松脱连接的杆件。拆下的杆配件应以安全的方式运出和吊下,严禁向下抛掷。在拆除过程中,应作好配合、协调工作,禁止单人进行拆除较重杆件等危险性的作业。 3.3.3严禁48和51钢管及其相应扣件混用。 3.3.4底立杆应按立杆接长要求选择不同长度的钢管交错设置,至少应有两种适合的不同长度的钢管作立杆。 3.3.5一定要采取先搭设起始段而后向前延伸的方式,当两组作业时,可分别从相对角开始搭设。 3.3.6杆件端部伸出扣件之外的长度不得小于100mm。3.3.7剪刀撑的斜杆与基本构架杆件之间至少有3道连接,其中斜杆的对接或搭接接头部位至少有一道连接。3.3.8脚手架底部应设一道扫地杆,大梁梁底处立杆必须设双扣件。4、安全事项 4.1搭设脚手架人员必须戴安全帽、系安全带、穿防滑鞋。 4.2在支架使用期间,严拆除主节点处的纵、横向水平杆纵横向扫地杆,连接杆等杆件。4.3搭拆脚手架时,地面应设围栏和警戒标志,并派专人看守。严禁非操作人员入内。4.3严格执行建筑施工扣件式钢管脚手架安全技术规范(J84-2001)和本企业安全标准中的有关安全条款。14